Thursday 14 July 2011
Today a part of the roof was replaced. This was done for security purposes.
Monday 4 July 2011
We added 2 new Rittal racks to our existing racks.
The new racks are the same model, but only with different doors. These doors take less space when working at the rear side off the rack.
Tuesday 28 June 2011
After 2 days of hard work, our datacenter is now cooled by a new Uniflair downflow cool unit. For the new Uniflair airco we needed to place some chillers on the roof.
Friday 17 June 2011
After 2 weeks of comparing cooling solutions we finally decided to go for the downflow cooling (with the free air cooling option) from Uniflair.
The units are ordered and will be arriving within the next 2 weeks.
Wednesday 1 June 2011
With a cooling specialist we looked at the possible cooling solutions for our data-center.
Tuesday 31 May 2011
The security cams are placed (inside and outside of the building).
Friday 27 May 2011
The first server has been placed in our datacenter. This means that the datacenter is almost ready, and more servers will be placed soon. The construction phase of the datacenter is almost complete.
Saturday 21 May 2011
The power grid is ready for use. The first 10 racks have each its own 16 ampere group with kWh meter.