Friday 13 January 2012
From the start of our datacenter we have reached a uptime of 100% for the year 2011.
We had only 2 small power disruptions, but the ups's did take over.
Tuesday 6 December 2011
The seconds build phase of our datacenter is started. We will expand our infrastructure.
We start with the new Ups systems, redundant power feeds, fire detection (vesda) and acces control.
The build will be completed in march-april.
Sunday 9 October 2011
Thanks to Trent fiber we were invited to the Military Boekelo.
Friday 23 September 2011
The first step in building the new power grid has been made. Today we received the MGE / APC Galaxy 5000 UPS. A Ups wich will power 30 racks for 10 minutes.
Friday 16 September 2011
The seconds row of 10 racks arived this day. A picture can be found here:
Wednesday 27 July 2011
Today we opened our doors to our brand new datacenter. All the construction has been completed and the datacenter is ready for use.
Friday 22 July 2011
Today we launched our new website. As you can see we replaced the design photo's with real photos. Also we translated the site to English.
Tuesday 19 July 2011
Today all the walls were painted, giving the datacenter the final touch before opening.
Saturday 16 July 2011
The co2 fire extinguishers are placed in the datacenter.